DIA FROM 110 mm to 500 mm , Total lengthes = 55.6 km

Proposed Water Networks: The diameters of the proposed water networks range from 110 mm to 500 mm, with a total length of 55.6 km.

Connection points on existing water networks: The proposed networks are connected to existing water networks surrounding the area. The number of connection points is five.

Designed length55.6 km
LocationEastern Province, Saudi Arabia
#
Project numberP415
ConsultantKUNHWA
Project details

Scope and technical highlights

  • DIA FROM 110 mm to 500 mm , Total lengthes = 55.6 km
  • Proposed Water Networks: The diameters of the proposed water networks range from 110 mm to 500 mm, with a total length of 55.6 km.
  • Connection points on existing water networks: The proposed networks are connected to existing water networks surrounding the area. The number of connection points is five.
Scope of work
Transimission LineWater System.Water Networks – Design
Water Networks – Design
Key quantities
55.6 km
Designed length