Single project / Pumping Stations / Eastern Cluster
Development works project for existing pumping stations and discharge lines in Al-Ahsa Governorate
Project detail
Overview
Project
overview.
OUT OF SCOPE (Site works only)
Total amount of Survey works: The total length of the Force mains are 69.4 km. The total area of the two Pumping stations works are 3,494 square meters.
Number Of BH: 41 BHS With 415 meters of Total depth
↗
Survey area2000 (m2) + 1494 (m2)⌁
Survey / line length64.6 km⌖
LocationAl-Ahsa, Eastern Province, Saudi Arabia#
Project numberP387Project details
Scope and technical highlights
- OUT OF SCOPE (Site works only)
- Total amount of Survey works: The total length of the Force mains are 69.4 km. The total area of the two Pumping stations works are 3,494 square meters.
- Number Of BH: 41 BHS With 415 meters of Total depth
Scope of work
SiteSite Works – ( Survey + Geotechnical )
Site Works – ( Survey + Geotechnical )
Key quantities
2000 (m2) + 1494 (m2)
Survey area
64.6 km
Survey / line length