Single project / Pumping Stations / Tanks & Reservoirs / Water Transmission / Eastern Cluster
Construction of 2 operational water tanks with a capacity of 100,000 m3 at the locations of AL-WAZIYAH an AL-GHWAIBAH
Project detail
Overview
Project
overview.
DIA FROM 400 mm to 1500 mm , Total lengthes = 26.5 km
OUT OF SCOPE (Site works only)
Water Pumping Station: It consists of two operational water tanks with a capacity of 100,000 m3.
Proposed Transmission Line: It consists of the following diameters: 1500 mm diameter, with a total length of 13 km. 1200 mm diameter, with a total length of 1.9 km. 1000 mm diameter, with a total length of 3.1 km. 600 mm diameter, with a total length of 8.3 km.
Total amount of Survey works: The total length of the Force main is 10.97 km.
Number Of BH: 10 BHS With 100 meters of Total depth
↗
Designed length26.5 km⌁
Capacity100,000 m3⌖
LocationEastern Province, Saudi Arabia#
Project numberAP209Project details
Scope and technical highlights
- DIA FROM 400 mm to 1500 mm , Total lengthes = 26.5 km
- OUT OF SCOPE (Site works only)
- Water Pumping Station: It consists of two operational water tanks with a capacity of 100,000 m3.
- Proposed Transmission Line: It consists of the following diameters: 1500 mm diameter, with a total length of 13 km. 1200 mm diameter, with a total length of 1.9 km. 1000 mm diameter, with a total length of 3.1 km. 600 mm diameter, with a total length of 8.3 km.
- Total amount of Survey works: The total length of the Force main is 10.97 km.
- Number Of BH: 10 BHS With 100 meters of Total depth
Scope of work
Water System - DesignSite Works (Survey + Geotechnical)Transmission LineWater Pumping StationWater Storage Facilities
Water System - Design + Site Works (Survey + Geotechnical)
Key quantities
26.5 km
Designed length
100,000 m3
Capacity
Project gallery
Project imagery.
2 images