Implementation of the city gate underground tank in Rabigh city – Rabigh Governorate
Single project / Tanks & Reservoirs / Western Cluster

Implementation of the city gate underground tank in Rabigh city – Rabigh Governorate

Project numberAP469
ClusterWestern Cluster
Program / Work orderGroup.02 Rabigh
OwnerNWC
Main consultantKUNHWA
ClassificationOperational Tank – Site Works (Survey+GEO)
Project detail
Overview

Project
overview.

Total amount of Survey works: Total works of the P.S are 20,000 m2.

Number Of BH: 2 BHS With 15 meters of Total depth

Total works of the P.S are 20,000 m2.

2 BHS

With 15 meters of Total depth

Survey area20000 (m2)
Boreholes2 BH
LocationRabigh, Saudi Arabia
#
Project numberAP469
Project details

Scope and technical highlights

  • Total amount of Survey works: Total works of the P.S are 20,000 m2.
  • Number Of BH: 2 BHS With 15 meters of Total depth
  • Total works of the P.S are 20,000 m2.
  • 2 BHS
  • With 15 meters of Total depth
Scope of work
SiteOperational Tank – Site Works (Survey+GEO)
Operational Tank – Site Works (Survey+GEO)
Key quantities
20000 (m2)
Survey area
2 BH
Boreholes