Implementation of main water distribution lines in the city of Mastura – Rabigh Governorate
Single project / Water Transmission / Western Cluster

Implementation of main water distribution lines in the city of Mastura – Rabigh Governorate

Project numberAP481
ClusterWestern Cluster
Program / Work orderGroup.13 Qadimiah
OwnerNWC
Main consultantKUNHWA
ClassificationWater Transmission Line – Site Works (Survey+GEO)
Project detail
Overview

Project
overview.

Total amount of Survey works: Transmission Line Works are 1.20 km.

Number Of BH: 1 BHS With 10 meters of Total depth

Transmission Line Works are 1.20 km.

1 BHS

With 10 meters of Total depth

Survey / line length1.20 km
Survey / line length1.2 km
LocationRabigh, Saudi Arabia
#
Project numberAP481
Project details

Scope and technical highlights

  • Total amount of Survey works: Transmission Line Works are 1.20 km.
  • Number Of BH: 1 BHS With 10 meters of Total depth
  • Transmission Line Works are 1.20 km.
  • 1 BHS
  • With 10 meters of Total depth
Scope of work
Transmission LineWater Transmission Line – Site Works (Survey+GEO)
Water Transmission Line – Site Works (Survey+GEO)
Key quantities
1.20 km
Survey / line length
1.2 km
Survey / line length