Construction of Water Transmission Main Interconnections from P1, GRC1 (Part 1)
Single project / Water Transmission / Western Cluster

Construction of Water Transmission Main Interconnections from P1, GRC1 (Part 1)

Project numberAD45-1
ClusterWestern Cluster
Program / Work order3
OwnerNWC
Main consultantKUNHWA
ClassificationWater Transmission Line – Design + Site Works (Survey+GEO)
Project detail
Overview

Project
overview.

DIA FROM 1400 mm to 1800 mm , Total lengthes = 7.70 km

Proposed Transmission Line: The water transmission line consists of the following: Diameter of 1400 mm with a total length of 6.30 km. Diameter of 1600 mm with a total length of 1.15 km. Diameter of 1800 mm with a total length of 0.25 km.

Total amount of Survey works: Transmission Line Works are 7.30 km.

Number Of BH: 6 BHS With 60 meters of Total depth

Diameter: Length (km)

1400 mm: 6.30

Designed length7.70 km
Survey / line length7.46 km
LocationWestern Region, Saudi Arabia
#
Project numberAD45-1
Project details

Scope and technical highlights

  • DIA FROM 1400 mm to 1800 mm , Total lengthes = 7.70 km
  • Proposed Transmission Line: The water transmission line consists of the following: Diameter of 1400 mm with a total length of 6.30 km. Diameter of 1600 mm with a total length of 1.15 km. Diameter of 1800 mm with a total length of 0.25 km.
  • Total amount of Survey works: Transmission Line Works are 7.30 km.
  • Number Of BH: 6 BHS With 60 meters of Total depth
  • Diameter: Length (km)
  • 1400 mm: 6.30
  • 1600 mm: 1.15
View full technical data +
  • 1800 mm: 0.25
Scope of work
Water Transmission Main InterconnectionsWater Transmission Line – Design + Site Works (Survey+GEO)(Survey+GEO)
Water Transmission Line – Design + Site Works (Survey+GEO)
Key quantities
7.70 km
Designed length
7.46 km
Survey / line length