Single project / Water Transmission / Western Cluster
Implementation of the main distribution network in Hali City – Al Qunfodhah Governorate
Project detail
Overview
Project
overview.
OUT OF SCOPE (Site works only)
Total amount of Survey works: Transmission Line Works are 39 km.
Number Of BH: 16 BHS With 80 meters of Total depth
Transmission Line Works are 73.59 km.
16 BHS
With 80 meters of Total depth
↗
Survey / line length73.59 km⌁
Survey / line length39 km⌖
LocationAl-Qunfudhah, Saudi Arabia#
Project numberP1115-2Project details
Scope and technical highlights
- OUT OF SCOPE (Site works only)
- Total amount of Survey works: Transmission Line Works are 39 km.
- Number Of BH: 16 BHS With 80 meters of Total depth
- Transmission Line Works are 73.59 km.
- 16 BHS
- With 80 meters of Total depth
Scope of work
Transmission LineWater Transmission Line – Site Works (Survey+GEO)
Water Transmission Line – Site Works (Survey+GEO)
Key quantities
73.59 km
Survey / line length
39 km
Survey / line length