Implementation of main distribution lines, including pumping works from the Gran Pumping Station – Khulais City
Single project / Water Transmission / Western Cluster

Implementation of main distribution lines, including pumping works from the Gran Pumping Station – Khulais City

Project numberAP466
ClusterWestern Cluster
Program / Work orderGroup.10 Khulais
ClassificationTransmission Lines
Project detail
Overview

Project
overview.

PDF package - 40 BHS

PDF package - With 240 meters of Total depth

LocationKhulais, Saudi Arabia
#
Project numberAP466
Project details

Scope and technical highlights

  • PDF package - 40 BHS
  • PDF package - With 240 meters of Total depth
Scope of work
Transmission LinesWorks (GEO)
Transmission Lines