Implementation of the main water distribution station for Al Sharif Reservoir (first phase)
Single project / Water Transmission / Western Cluster

Implementation of the main water distribution station for Al Sharif Reservoir (first phase)

Project numberAP431
ClusterWestern Cluster
Program / Work orderWestern Cluster - 2
OwnerNWC
Main consultantIDOM
ClassificationTransmission line - Design
Project detail
Overview

Project
overview.

DIA FROM 300 mm to 1200 mm , Total lengthes = 15.40 km

Proposed transmission line: The diameters of the proposed transmission line range is from 300 mm to 1,200 mm, with a total length of 15 km.

Designed length15.40 km
StatusApproved
LocationWestern Region, Saudi Arabia
#
Project numberAP431
Project details

Scope and technical highlights

  • DIA FROM 300 mm to 1200 mm , Total lengthes = 15.40 km
  • Proposed transmission line: The diameters of the proposed transmission line range is from 300 mm to 1,200 mm, with a total length of 15 km.
Scope of work
Transimission LineTransmission line - Design
Transmission line - Design
Key quantities
15.40 km
Designed length